After Division 2 of Part 11 of the Building Act 1993 insert —
(1) A person to whom a decision of the Building Practitioners Board under Division 1 or 2 applies may apply to the Victorian Civil and Administrative Tribunal for a review of—
(a) that decision; or
(b) a failure of the Board to make that decision within a reasonable time.
(2) If the Authority referred a matter to the Building Practitioners Board for inquiry under Division 2, the Authority may apply to the Victorian Civil and Administrative Tribunal for a review of—
(a) a failure by the Board to conduct an inquiry, within a reasonable time, into the matter referred to it; or
(b) a refusal by the Board to conduct the inquiry; or
(c) a decision by the Board on the inquiry.
(3) A person who requested the Building Practitioners Board to conduct an inquiry under Division 2 may apply to the Victorian Civil and Administrative Tribunal for a review of—
(a) a failure by the Board to conduct the inquiry within a reasonable time; or
(b) a refusal by the Board to conduct the inquiry; or
(c) a decision by the Board on the inquiry.".