HERITAGE ACT 2017 (NO. 7 OF 2017) - SECT 97

Time for determining permit applications

    (1)     Subject to section 99, the Executive Director must determine a permit application within 60 days after receiving the application unless that period is extended in accordance with this section.

    (2)     The Heritage Council, on the application of the Executive Director, may extend the period of 60 days by a further period of up to 60 days.

    (3)     An application by the Executive Director under subsection (2) must be made before the end of the period of 60 days specified in subsection (1).