MAJOR TRANSPORT PROJECTS FACILITATION ACT 2009 (NO. 56 OF 2009) - SECT 216
Project authority or utility can commence dispute resolution procedure after end of negotiation period
If the parties have not entered into a utility agreement within the
negotiation period, either of the parties may give written notice to the other
party that a dispute exists to which this Division applies.