Content of impact management plans

        A project proponent for a declared project must prepare an impact management plan for the project that—

        (a)     complies with the scoping directions for that plan; and

        (b)     contains an assessment of the impacts of the declared project; and

        (c)     sets out the options for the development of the declared project that have been considered, and the impacts for those options; and

        (d)     sets out the methods considered to avoid, minimise, manage or offset the impacts referred to in paragraph (b) or (c); and

        (e)     includes a description of the preferred option for the development of the declared project and the reasons for that preference; and

        (f)     sets out how any State environment protection policy or any waste management policy that applies in relation to the development and use of the declared project will be observed; and

        (g)     identifies all of the applicable approvals that will be required under all applicable laws in order for the declared project to be developed, including any requirements under those laws applying to the declared project when assessing the impacts of the declared project; and

        (h)     includes the information that would be required for the applicable law decisions to be made under all of the applicable laws that apply to the project including—

              (i)     a list of the mandatory applicable law criteria and discretionary applicable law criteria; and

              (ii)     information as to how the proponent considers the criteria referred to in subparagraph (i) apply.