MAJOR TRANSPORT PROJECTS FACILITATION ACT 2009 (NO. 56 OF 2009) - SECT 74

Specific applicable approval—Environment protection works approvals

    (1)     This section applies if a works approval is required under the Environment Protection Act 1970 in order for the declared project or a part of the declared project to be developed.

    (2)     An assessment committee must give a copy of its assessment committee recommendation to the EPA on the same day on which the committee gives the Planning Minister its assessment committee recommendation.

    (3)     On receiving an assessment committee recommendation under this section, the EPA may give advice to the Planning Minister as to—

        (a)     whether the Minister should, as part of the Minister's approval decision, issue a works approval for the declared project or a part of the declared project; and

        (b)     if a works approval should be issued, whether it should be subject to conditions and the nature of such conditions (if any).

    (4)     The EPA must give its advice to the Planning Minister within 30 business days after receiving the copy of the assessment committee recommendation.